Main Search Forums Advanced Search Disclaimer

Bharat Sanchar Nigam Ltd. &Amp; ... vs Motorola India Pvt. Ltd on 15 September, 2008

Cites 10 docs - [View All]

The Arbitration And Conciliation Act, 1996

Section 28 in The Arbitration And Conciliation Act, 1996

State Of Karnataka Etc vs Shri Rameshwara Rice Mills ... on 24 February, 1987

Datar Switchgears Ltd vs Tata Finance Ltd. & Anr on 18 October, 2000

Section 4 in The Arbitration Act, 1940 1


Loading...
Supreme Court of India
Bench: Chatterjee]
      REPORTABLE

               IN THE SUPREME COURT OF INDIA

                 CIVIL APPELLATE JURISDICTION

                 CIVIL APPEAL NO.5645 OF 2008

              [Arising out of SLP(C) No. 3459 of 2007] Bharat Sanchar Nigam Ltd.
& Anr. .......Appellants Versus

     Motorola India Pvt. Ltd. ....Respondent  JUDGMENT

     TARUN CHATTERJEE, J.

1. Leave granted.

2. This appeal is directed against the judgment and final order  dated 26th of
October, 2006 of the High Court of Kerala at  Ernakulam in AR No 18 of 2006
whereby, the High Court  had allowed the prayer for appointment of the
arbitrator at  the instance of the respondents and directed the parties to
submit their disputes to arbitration.

3. The pivotal questions that need to be decided in this appeal  are:

         i) Whether the levy of liquidated damages under  clause 16.2 of the
tender document is an 2

 "excepted matter" in terms of clause 20.1 of the  said document so
that the same cannot be  referred to arbitration or looked into by the
arbitrator.

       ii) Whether clause 62 of the special conditions of  the tender document
will prevail over clause 16.2  of the general conditions of the contract.

4. The relevant facts, which would assist us in appreciating  the controversy
involved are narrated in a nutshell, which  are as follows:

             The appellant had issued a notice inviting tender  dated 4th of
January, 2001, calling upon the eligible  bidders for turn key project on
planning, engineering,  supply, installation and commissioning of Indian Mobile
Personal Communications System in the telecom circles  of Kerala, Karnataka,
Tamil Nadu and Andhra Pradesh.  The respondent submitted its bid in response to
the  notice inviting tender and after the technical, commercial  and financial
bid evaluation, the respondent was 3

 awarded the tender and an Advance Purchase Order  (APO) dated 5th of September,
2001 for phase I and Phase  II was issued to it by the appellant. The purchase
order  provided, inter alia, the terms for payment and the  schedule for
delivery of the goods. It also provided for  liquidated damages in the event of
failure on the part of  the respondent to meet with the delivery schedule.
Clause 16.2 of the general conditions of the tender  document provided for
liquidated damages to the extent  of 0.5% of the value of the delayed quantity
of the goods  and services for each week of delay or the part thereof for  a
period of upto 10 weeks and thereafter charge 0.7% of  the value of delayed
quantity or part thereof, for a period  of upto 10 weeks thereafter. It is the
case of the  appellants that the respondent had failed to complete  phase I and
phase II of the project within the schedule as  provided in the tender document,
and therefore,  liquidated damages were imposed by the Tamil Nadu  Circle of the
appellant on 21st of May, 2004 under clause  16.2 of the tender document,
quantification of which was 4

 beyond the purview of the arbitration agreement. There  was an exchange of
correspondence between the Tamil  Nadu Circle of the appellant alleging the
delay in the  purchase of goods and the respondents denying any  such delay and
objecting to the levy of liquidated  damages. On 24th of March, 2006, the
respondent  invoked the arbitration clause by sending a letter  through its
counsel to the appellants to which they did  not concede and justified the
imposition of liquidated  damages. The respondent filed an arbitration
application  before the High Court of Kerala at Ernakulam for the  appointment
of arbitrator under section 11 of the  Arbitration and Conciliation Act, 1996 in
respect of the  liquidated damages assessed by the appellant. In the  counter
affidavit filed in the High Court, the appellant  alleged that the liquidated
damages assessed and  quantified by the appellant under clause 16.2 of the
tender document was an excepted matter as per clause  20.1 of the said document
and, therefore, not arbitrable.  The High Court, as noted herein earlier, by the
impugned 5

 judgment allowed the arbitration request of the  respondents holding that the
imposition of liquidated  damages by the appellant was not an "excepted
matter"  and therefore, subject to arbitration. It is this judgment  of the
High Court, which is impugned in this appeal, in  respect of which leave has
already been granted.

5. Before proceeding further, we deem it appropriate to note  the relevant
clauses of the tender document and the  purchase order, which would assist us in
determining  whether the matters alleged are an excepted matter.  Clause 16.2
reads as under:-

          "16.2. Should the tenderer fail to deliver the goods and services
on turn key basis within the period prescribed, the purchaser shall be entitled
to recover 0.5% of the value of the delayed quantity of the goods &
services, for each week of delay or part thereof, for a period upto 10 weeks and
thereafter at the rate of 0.7% of the value of the delayed quantity of the goods
and services for each week of delay or part thereof for another 10 weeks of
delay. In the present case of turn key solution of supply, installation and
commissioning, where the delayed portion of the delivery and provisioning of
services materially hampers effective user of the systems, Liquidated Damages
charged shall 6

 be levied as above on the total value of the concerned package of the purchase
order. Quantum of liquidated damages assessed and levied by the purchaser shall
be final and not challengeable by the supplier."

  Clause 20.1 which is the arbitration clause and provides  for excepted
matters, i.e., those matters the decision to  which is specifically provided in
the agreement itself  reads as under:-

     20.1 In the event of any question, dispute or difference arising under this
agreement or in connection there-with (except as to the matters, the decision to
which is specifically provided under this agreement), the same shall be referred
to the sole arbitration of the CGM, Kerala Telecom Circle, BSNL or in case his
designation is changed or his office is abolished, then in such cases to the
sole arbitration of the officer for the time being entrusted (whether in
addition to his own duties or otherwise) with the functions of the CGM, Kerala
Telecom Circle, BSNL or by whatever designation such an officer may be called
(hereinafter referred to as the said officer), and if the CGM Kerala Telecom
Circle or the said officer is unable or unwilling to act as such, then to the
sole arbitration of some other person appointed by the CGM, Kerala Telecom
Circle or the said officer. The agreement to appoint an arbitrator will be in
accordance with the Arbitration and Conciliation Act, 1996. 7

 There will be no objection to any such appointment on the ground that the
arbitrator is a Government Servant or that he has to deal with the matter to
which the agreement relates or that in the course of his duties as a government
servant he has expressed his views on all or any of the matters in dispute. The
award of the arbitrator shall be final and binding on both the parties to the
agreement. In the event of such an arbitrator to whom the matter is originally
referred, being transferred or vacating his office or being unable to act for
any reason whatsoever, the CGM, Kerala Telecom Circle, BSNL or the said officer
shall appoint another person to act as an arbitrator in accordance with the
terms of the agreement and the person so appointed shall be entitled to proceed
from the stage at which it was left out by his predecessors.........."

  Clause 15.2 of Section III of the tender document, which  deals with the
"delays in the supplier's performance"  reads as under:

     "Delay by the Supplier in the performance of its delivery obligations
shall render the Supplier liable to any or all of the following sanctions,
forfeiture of its performance security, imposition of liquidated damages, and/or
termination of the contract for default".

                                                                8

 Clause 62 of Section IV of the tender document which  deals with liquidated
damages and incentive reads as  under:-

          "The bidder shall be charged liquidated damages at the rates as
defined in the General conditions of contract as contained in Section III for
any delay in the turnkey job entrusted to the bidder. However he shall be
provided an incentive @ 0.5% of the cost of the network of each service area
(Telecom Circle), for each week of early commissioning of the entire network in
that service area, subject to a maximum of 3% of the value of the contract of
the circle".



6. Since this appeal arises out of an order, which appointed  an arbitrator, to
decide the dispute referred to by the  respondent, we, in this appeal, need to
decide that whether  in view of the arbitration clause in the tender document
provided under clause 20 of the said document, the breach  specified in 16.2 is
an "excepted matter".

7. Mr. Gopal Subramaniam, Additional Solicitor General of  India appearing on
behalf of the appellant contended that  in view of the decision of this Court in
Vishwa Nath Sood 9

 vs. UOI [(1989) 1 SCC 657], a conjoint reading of clause  16.2 and clause 20.1
would clearly show that clause 16.2 is  covered under the excepted matters as
provided in clause  20.1 of the tender document. He further contended that the
High Court had erred in holding that the quantification of  the liquidated
damages was subsequent to the decision of  liability of liquidated damages to be
payable to the  appellant. Therefore, he contended that the respondent had
specifically subscribed to each and every clause of the  agreement without any
objection at the tender stage and  accordingly, it was not open to them to claim
immunity  from the contractual obligations. Thus, the matter in  respect of
which the respondent sought reference to  arbitration was "excepted
matter" in terms of clause 16.2 of  the tender agreement.

       In order to satisfy us in the aforesaid contentions,  the learned
Additional Solicitor General, Mr. Gopal  Subramanium placed strong reliance in
the case of Food  Corporation of India Vs. Sreekanth Transport 1999 10

 (4) SCC 491, which has given the following principles  relating to
"Excepting matters" as under :-  "1. These appeals by the grant
of Special Leave pertains to the effect of the usual `excepted clause' vis-`-vis
the arbitration clause in a Government contract. While it is true and as has
been contended, that the authorization of the arbitrators to arbitrate, flows
from the agreement but the High Court in the judgment impugned

          thought it fit to direct adjudication of `excepted matters' in the
agreement itself by the arbitrators and hence these appeals before this Court.

          2. At the outset, it is pertinent to note that in the usual Government
contracts, the reference to which would be made

          immediately hereafter, there is exclusion of some matters from the
purview of

          arbitration and a senior officer of the Department usually is given
the authority and power to adjudicate the same. The

          clause itself records that the decision of the senior officer, being
the adjudicator, shall be final and binding between the parties - this is what
popularly known as `excepted matters' in a Government or

          Governmental agencies' contract.

          3. `Excepted matters' obviously, as the parties agreed, do not require
any further adjudication since the agreement itself provides a named adjudicator
- concurrence to the same obviously is

          presumed by reason of the unequivocal

          acceptance of the terms of the contract by 11

 the parties and this is where the courts have found our lacking in its
jurisdiction to entertain an application for reference to arbitration as regards
the disputes arising therefrom and it has been the consistent view that in the
event the claims arising within the ambit of excepted matters,

          question of assumption of jurisdiction of any arbitrator either with
or without the intervention of the court would not arise; the parties themselves
have decided to have the same adjudicated by a particular officer in regard to
these matters; what are these exceptions however are questions of fact and
usually mentioned in the contract documents and forms part of the

          agreement as such there is no ambiguity in the matter of adjudication
of these

          specialized matters and termed in the

          agreement as the excepted matters....."    Keeping the aforesaid
principles in mind, let us  proceed further.

     We may keep on record that the appellants alleged  that respondents had not
completed phase I and phase II  of the project within the schedule as provided
in the  tender document whereupon the appellants had to  impose liquidated
damages and invoke clause 16.2 of the  tender document. But the respondents
refuted these 12

 allegations. The contention of the respondent in this case  was that the delay,
if any, was caused due to the  appellant's delay in supplying necessary inputs
to the  respondent. So the respondent contends that it had  performed its part
of the contract in time and the blame  for delay lies on the appellant. Thus it
is to be noted that  there is a dispute between the parties on the question
whether any breach was committed in this case.

8. The appellant had contended before the High Court of  Kerala that the levy of
the liquidated damages on the  respondent was a matter outside the purview of
the scope  of arbitration proceedings as it "squarely falls within the
exception provided under Clause 20 of Section III, being the  matters for which
mode of decision is provided under the  Agreement itself."

          The respondent on the other hand contended that  the claim of the
petitioner that the dispute pertaining to  levy of liquidated damages falls
outside the arbitration  agreement being an excepted matter is fallacious. 13

 The High Court held that there was no reason why  the arbitration request on
behalf of the respondent  should not be allowed. It held that clause 16.2 is not
an  excepted matter under clause 20 of the tender document.

9. Having heard the learned counsel for the parties and after  examining the
judgment of the High Court and the other  materials on record, we are of the
view that this appeal  must be dismissed. Clause 20 is the arbitration clause
and  provides that any question, dispute or difference arising  under this
agreement or in connection therewith would be  referred to arbitration. To this,
an exception is also provided  which lays down that the matters, the decision to
which is  specifically provided under this agreement, would not be  referred to
arbitration. From a bare reading of clause 16.2  of Section III of the tender
document, it is clear that if the  tenderer fails to deliver the goods and
services on turnkey  basis within the period prescribed, the purchaser shall be
entitled to recover liquidated damages and the quantum of  the liquidated
damages assessed and levied by the 14

 purchaser shall be final and not challengeable by the  supplier.



10. We are in full agreement with the findings of the High  Court that there was
a dispute as to whether the  respondent had at all acted in breach of any terms
and  conditions of the tender document.

          The question to be decided in this case is whether  the liability of
the respondent to pay Liquidated Damages  and the entitlement of the appellant,
to collect the same  from the respondent is an excepted matter for the  purpose
of clause 20.1 of the General Conditions of  contract. The High Court has
pointed out correctly that  the authority of the purchaser (BSNL) to quantify
the  Liquidated Damages payable by the supplier Motorolla  arises once it is
found that the supplier is liable to pay  the damages claimed. The decision
contemplated under  clause 16.2 of the agreement is the decision regarding  the
quantification of the Liquidated Damages and not  any decision regarding the
fixing of the liability of the 15

 supplier. It is necessary as a condition precedent to  find that there has been
a delay on the part of the  supplier in discharging his obligation for delivery
under the agreement.

  It is clear from the reading of clause 15.2 that the  supplier is to be held
liable for payment of liquidated  damages to the purchaser under the said clause
and not  under clause 16.2. The High Court in this regard  correctly observed
that it was not stated anywhere in  clause 15 that the question as to whether
the supplier  had caused any delay in the matter of delivery will be  decided
either by the appellant/BSNL or by anybody who  has been authorized on the terms
of the agreement.  Reading clause 15 and 16 together, it is apparent that
clause 16.2 will come into operation only after a finding  is entered in terms
of clause 15 that the supplier is liable  for payment of liquidated damages on
account of delay  on his part in the matter of making delivery. Therefore,
clause 16.2 is attracted only after the supplier's liability 16

 is fixed under clause 15.2. It has been correctly pointed  out by the High
Court that the question of holding a  person liable for Liquidated Damages and
the question of  quantifying the amount to be paid by way of Liquidated  Dmages
are entirely different. Fixing of liability is  primary, while the
quantification, which is provided for  under clause 16.2, is secondary to it.
There is no provision in the agreement, apparent on  the face of it, relating to
a decision made by any specified  authority on the issue of levy of Liquidated
Damages, as  is contemplated under clause 20.1 of the agreement  which is
excepted from the purview of arbitration. No  decision coming within the scope
of excepted matters  under clause 20.1 is envisaged by any portion of the
agreement regarding the liability of the supplier to  liquidated damages.

     Quantification of liquidated damages may be an  excepted matter as argued
by the appellant, under  clause 16.2, but for the levy of liquidated damages,
there 17

 has to be a delay in the first place. In the present case,  there is a clear
dispute as to the fact that whether there  was any delay on the part of the
respondent. For this  reason, it cannot be accepted that the appointment of the
arbitrator by the High Court was unwarranted in this  case. Even if the
quantification was excepted as argued  by the appellant under clause 16.2, this
will only have  effect when the dispute as to the delay is ascertained.  Clause
16.2 cannot be treated as an excepted  matter because of the fact that it does
not provide for any  adjudicatory process for decision on a question, dispute
or difference, which is the condition precedent to lead to  the stage of
quantification of damages.  The above stated position can be ascertained
through the judgment of this Court in the case of State  of Karnataka vs. Shree
Rameshwara Rice Mills,  (1987) 2 SCC 160. This Court in the said case, made a
clear distinction between adjudicating upon an issue  relating to a breach of
condition of contract and the right  to assess damages arising from a breach of
condition. It 18

 was held that the right conferred to assess damages  arising from a breach of
condition does not include a  right to adjudicate upon a dispute relating to the
very  breach of conditions and that the power to assess  damages is a subsidiary
and consequential power and  not the primary power.

  11.Clause 20.1 regarding excepted matters reads "In the event  of any
question, dispute or difference arising under this  agreement or in connection
there-with (except as to the  matters, the decision to which is specifically
provided  under this agreement)...". Therefore it is clear from this
provision, matters which will not fall within the arbitration  clause are
questions, disputes or differences, the decision  to which is specifically
provided under the agreement.  Clause 16.2 is not a clause where in any decision
making  power is specifically provided for with regard to any  question, dispute
or difference between the parties relating  to the existence of breach or the
very lack of liability for  damages, i.e. the levy of Liquidated Damages. 19

   12.The learned senior counsel for the appellant relied on the  decisions of
this court in Vishwanath Sood vs. UOI  [(1989) 1 SCC 657], and General Manager,
Northern  Railway vs. Sarvesh Chopra [(2002) 4 SCC 45]. These  cases, we are
afraid, will not be of any help to the  appellants being distinguishable on
facts and having  different contractual clauses. We may note that clause 16.2
cannot be treated as an excepted matter. This is because  admittedly, it does
not, provide for any adjudicatory process  for decision on a question, dispute
or difference, which is  the condition precedent to lead to the stage of
quantification of damages nor is it a no claim or no liability  clause.

  In Vishwanath Sood's case (supra), it was held by  this court that a
particular claim of the government was  excluded because the Superintendent
Engineer acted as  the revisional authority to decide disputes between the  two
parties by an adjudicatory process, there being a 20

 complete machinery for settlement of the disputes in the  relevant clause and
most importantly, the  Superintendent Engineer had the discretion on
consideration of the facts and circumstances including  mitigating facts, held
no damages was payable. Again in  the case of Sarvesh Chopra, this court had
held that the  claims covered by the no claims clause, i.e., where the
contractor had given up the right to make a claim for  breach on the part of the
government was not arbitrable  in terms of the arbitration clause contained
therein and  clause 63 of the general conditions of the contract which  provided
for exclusion because no claim clause was  excepted as such claims were simply
not entertainable.  In view of the discussions made hereinabove, we hold  that
the disputes raised by the respondents are  arbitrable and not excepted from
scope of arbitration.    13.We feel that there are certain other issues that are
to be  discussed while disposing of this appeal. The respondent  contended in
its written submission filed before this court 21

 on 14th May, 2007 that the quantum of damages calculated  by the appellant in
respect of clause 16.2 of the tender  document, simply cannot have the effect of
rendering all the  above disputes as not being arbitrable. We find that there is
considerable merit in this argument. The true essence of  any arbitration
agreement is to arbitrate the matters in a  cordial way in respect of issues
where there is a dispute  between the parties. To construe such limited words in
clause 16.2 as being so all encompassing would destroy the  very foundation of
the bargain between the parties. The  appellant in the present case is acting in
an unfair way by  seeking to exclude, from arbitration, what it has agreed to
arbitrate in the first place.

14.The appellant contended that it has the unilateral right to  determine the
Liquidated damages under clause 16.2 and  that the quantum of Liquidated Damages
decided by the  appellant, even if it is exorbitant, would be final and cannot
be challenged. We find the contention of the respondent  that if the said
contention of the appellant is supported, it  would mean that a party would be
held liable to damages of 22

 whatever amount the other party demands without  recourse to a remedy, to be
relevant and should be given  due importance. Such a contention by the appellant
would  be in violation of Section 28 and Section 74 of the Indian  Contract Act.

  15.The learned counsel of the appellants had submitted before  this court that
it was the appellant, which had the right to  appoint the arbitrator. This
submission cannot be accepted.  The respondent had invoked the arbitration
clause on the  ground that there was no delay on its part by sending a  letter
to this effect to the appellants on 24th of March, 2006.  On 25th April, 2006,
the appellants/BSNL replied stating  that they had rightly recovered the
Liquidated Damages and  that the recovery of the damages was not arbitrable. The
appointing authority in this matter, i.e., CGM Kerala, did  not respond to the
notice requiring the appointment of  arbitrator and failed to act within the
time prescribed under  the Arbitration and Conciliation Act 1996. Since the
appointing authority appointed no arbitrator, the 23

 respondent/Motorolla, on 25th of May, 2006, filed a petition  under Section 11
of the said Act before the High Court at  Kerala. In the case of Datar
Switchgear vs. Data Finance  Lt. [(2000) 8 SCC 151], which was affirmed in Punj
Llyod  Ltd. vs. Petronet MHB Ltd. [(2006) 2 SCC 638], it was  held that once a
minimum of 30 days is expired and a  petition is filed to the court, the
appointing authority loses  the right to make the appointment. Therefore, the
appellant/BSNL has now lost its right to appoint any  arbitrator for settling
the disputes under the agreement.    16.Further, CGM Kerala Circle has already
taken a decision as  is evident from his letter dated 25th of April, 2006, that
the  appellant was right in imposing the liquidated damages and  therefore, the
question of such a person becoming an  arbitrator does not arise as it would not
satisfy the test of  impartiality and independence as required under Section  12
of the Arbitration and Conciliation Act, 1996. Moreover  it would also defeat
the notions laid down under the  principles of natural justice wherein it has
been 24

 recognized that a party cannot be a judge in his own  cause. The judgment of
this Court in State of Karnataka  vs. Shree Rameshwara Rice Mills, (1987) 2 SCC
160, is  significant in this matter. The Court had stated:  ".....Even
assuming that the terms of Clause 12 afford scope for being construed as
empowering the officer of the State to decide upon the question of breach as
well as assess the quantum of damages, adjudication by the officer regarding the
breach of the contract can not be sustained under law because a party to the
agreement cannot be an arbiter in his own cause. Interest of justice and equity
require that where a party to a contract disputes the committing of any breach
of conditions the adjudication should be by an independent person or body and
not by the other party to the contract".

 17.The provision under clause 16.2 that quantification of the  Liquidated
Damages shall be final and cannot be  challenged by the supplier Motorolla is
clearly in restraint  of legal proceedings under section 28 of the Indian
Contracts Act. So the provision to this effect has to be held  bad.

                                                             25

 18.Pursuant to section 4 of the Arbitration and Conciliation  Act, 1996, a
party who knows that a requirement under the  arbitration agreement has not been
complied with and still  proceeds with the arbitration without raising an
objection,  as soon as possible, waives their right to object. The High  Court
had appointed an arbitrator in response to the  petition filed by the appellant.
At this point, the matter was  closed unless further objections were to be
raised. If further  objections were to be made after this order, they should
have been made prior to the first arbitration hearing. But  the appellant had
not raised any such objections. The  appellant therefore had clearly failed to
meet the stated  requirement to object to arbitration without delay. As such
their right to object is deemed to be waived.    19.Finally we are of the
opinion that the contention of the  Respondent that Clause 62 referring to
special clauses has  an overriding effect on Clause 16.2, cannot be accepted..
There is in fact no conflict between clause 62 and 16.2.  Clause 62 has two
parts in it. One part referring to the 26

 Liquidated damages and the other part refers to incentives  in case the
respondent/Motorolla performs its part of the  contract within time. The part
dealing with Liquidated  Damages under clause 62 in fact refers it back to
clause  16.2 dealing with the quantification of Liquidated Damages.  So it is
apparent that there is no dispute between clause 62  and clause 16.2.

  20.For the reasons aforesaid, we are of the view that the High  Court was
justified in passing the impugned judgment and  there is no infirmity in the
impugned order for which we  can interfere with the order of the High Court. The
appeal is  therefore dismissed. There will be no order as to costs.
................................J.

                                               [Tarun Chatterjee]

  New Delhi; ...................................J. September 15, 2008.
[Lokeshwar Singh Panta]

 27

 28