time is of the essence of the contract. Save in mercantile contracts stipulations as to time are, in the absence ... essence of the contract. The question is whether these contracts can be regarded as mercantile contracts. Mercantile contracts
Patna High Court
- Cites 32 - Cited by 10 -
AIR 1957 Pat 586
- K Singh
essence of contract. Fixation of period within which the contract is to be performed does not make stipulation as time ... essence of the contract, then the contract does not become voidable on failure to perform the contract within the fixed
Gujarat High Court
- Cites 13 - Cited by 1 -
(1993) 1 GLR 28
- J Bhatt
obligations required to be performed by them under the CONTRACT the relative obligation of the party affected by such Force ... COMPENSATION FOR DELAY (LIQUIDATED DAMAGES): 27.1 Time is the essence of the CONTRACT. In case the CONTRACTOR fails to complete
Delhi High Court
- Cites 73 - Cited by 0 - G Mittal
Court dismissed the suit stating that the time is essence of contract, the suit is barred by limitation ... Suit. 8.Suit is barred by limitation  Time is essence of contract: (i)Admittedly, the suit property was purchased
Madras High Court
- Cites 57 - Cited by 0
part of the contract? (2) Is the time essence of the contract? (3) If so, whether the termination ... fixed time, in contracts in which time is essential. The question whether time is the essence of the contract, with
Supreme Court of India
- Cites 33 - Cited by 0
willingness. 2.3. He contended further that time was essence of contract is to be gathered from the surrounding circumstances ... support of his contention with regard to time as essence of contract, Mr. Dasgupta relied on Chand Rani v. Kamal
Calcutta High Court
- Cites 37 - Cited by 0 -
AIR 2003 Cal 263
- D Seth
obligations required to be performed by them under the CONTRACT the relative obligation of the party affected by such Force ... COMPENSATION FOR DELAY (LIQUIDATED DAMAGES): 27.1 Time is the essence of the CONTRACT. In case the CONTRACTOR fails to complete
Delhi High Court
- Cites 73 - Cited by 0 - G Mittal
make the stipulation as to time of the essence of the contract. Intention to make 228 time of the essence ... make the stipulation as to time of the essence of the contract. It is true that appellants
Supreme Court of India
- Cites 2 - Cited by 143 -
1967 AIR 868
case the parties did intend to make time the essence of the contract. Though the learned Single Judge ... though as a general proposition of law time is not the essence of the contract in the case
Supreme Court of India
- Cites 7 - Cited by 111 -
AIR 1993 SC 1742
- S Mohan
parties that time should be of the essence of the contract, the contract does not become voidable by the failure ... essence of contract: "1. Where the parties have expressly stipulated in their contract that the time fixed for performance must
Supreme Court of India
- Cites 13 - Cited by 108 - Banerjee