Filter Results by
Document Types
All
1 - 10 of 202 (1.14 seconds)

took note of the continuous price rise and CPWD cost index while awarding ... submits that the claimant-appellant had placed the CPWD cost index as well as evidence of tenders accepted
Delhi High Court
- Cites 3 - Cited by 0 - Full Document
that the arbitrator has erroneously relied upon the CPWD cost index which does not amount to a statutory increase ... cost escalation made on the basis of the CPWD cost index could not form the basis of awarding an amount
Delhi High Court
- Cites 16 - Cited by 7 - Full Document
Clause 10-C of the agreement. The CPWD Cost Index which had shown 113 per cent escalation was reduced ... some material which was in the form of CPWD Cost Index which is not issued
Delhi High Court
- Cites 7 - Cited by 2 - Full Document
Delhi High Court Union Of India vs M/S. Goel Construction Co. & Anr. on
Delhi High Court
- Cites 9 - Cited by 0 - Full Document
note of the continuous price rise and the CPWD cost index, while awarding
Delhi High Court
- Cites 11 - Cited by 0 - Full Document
basis of averaging the increase in the CPWD cost Index. (Computed for 3 years from the date of booking ... cost index will be as applicable to the plinth area for Delhi and as followed/laid down by CPWD from
National Consumer Disputes Redressal
- Cites 1 - Cited by 0 - Full Document
Delhi District Court Union Of India vs (2) Sh. Vinod Kumar Malik on 16 April
Delhi District Court
- Cites 15 - Cited by 0 - Full Document
Arbitrator has relied on CPWD Cost CS No.-220/09 Page No. 6/14 Index, 1992 and stated that ... Arbitrator is based on the CPWD cost index as on 01.06.1998 when the area rate
Delhi District Court
- Cites 11 - Cited by 0 - Full Document
increase on the basis of the cost index applying the CPWD Manual. It was held that no fault could ... arbitrator in finding that the building cost index calculated by the CPWD is the rightly recognised method of working
Delhi High Court
- Cites 28 - Cited by 5 - Full Document
cost of construction. The indices issued by CPWD reveal that the cost index in January,1990 was 506. It rose ... arisen to 1211. On the cost index of 506 for January,1990, CPWD Schedule shows that cost of construction
Delhi High Court
- Cites 0 - Cited by 1 - Full Document